Job
Number |
Bid Info |
Project Title |
Location |
Project Manager |
Construction
Period |
Percent Complete |
Comments |
| 230507 |
|
Jordan River Parkway Trail Improvements:
Trail Under I-80 at 200 South |
600 North and 700 North, 1400 West to 1600
West |
Dell Cook |
Jun-2009 to Aug-2009 |
0% |
Contractor: J. Lyne Roberts & Sons |
| 231009 |
|
Riverside Park Streetscape Improvements |
|
Dell Cook |
Jan-2009 to Jun-2009 |
95% |
Contractor: Utah Sprinkler and Landscape |
| 241501 |
|
City Parks ADA Accessibility: Reservoir
Park and Rosewood Park |
|
Dell Cook |
May-2009 to Jul-2009 |
25% |
Contractor: A-Z Landscaping |
| 251601 |
|
Shipp Park |
579 4th Ave |
Dell Cook |
Jun-2009 to Aug-2009 |
0% |
|
| 260142 |
|
Jordan River Parkway Trail: Security
Lighting |
Constitution Park to Rose Park Golf Course
Bridge |
Dell Cook |
Jun-2009 to Sep-2009 |
0% |
Contractor: B. Jackson Construction |
| 260144 |
|
Jordan River Parkway Trail: Rose Park Golf
Course to Redwood Road |
|
Dell Cook |
Mar-2009 to Jun-2009 |
99% |
Contractor: Dymock Construction |