1300 South Reconstruction

 


1300 South Roadway Reconstruction (State St to 400 West)

Geneva Rock is the contractor that will implement this project.  The contractor will be coordinating with businesses and residents for access during construction.  One lane of traffic will be provided in each direction (north to south and east to west) on the sections under construction. 

PLEASE UTILIZE ALTERNATE ROUTES DURING CONSTRUCTION (see map).

This project will include the following improvements to 1300 South from the west side of State Street to the east side of 400 West:

  • Replacement of concrete street
  • Replace all damaged sidewalk, curb and gutter
  • Replace crosswalks at 300 West, West Temple Street, Richards Street, Main Street and State Street
  • Local businesses will remain open during construction and reasonable access will be provided.

 

Project Schedule

Construction Status: 

Construction Begins:  June 23, 2014

120 Days from Start: Estimated completion of construction

 

Contact Information

We want to hear from you.  Call us, or send us an email with your questions and comments!

Salt Lake City Public Involvement Coordinator:  Lani-Eggertsen-Goff, 801-535-6240, lani.eggertsen-goff@slcgov.com

Salt Lake City Project Manager: John Coyle, 801-535-6241, john.coyle@slcgov.com

Salt Lake City Project Representative:  Ken Johnson, 801-535-6696, kenneth.johnson@slcgov.com

 

Thank you for your patience and coorperation as Salt Lake City works to improve the City's roadways.